(#8540) Renewable energy compliance using solar farm within project complex

Query

We have installed a Solar farm Unit within the larger project complex with a total installed capacity of 300KW(peak). Since the office building project registered with GRIHA is small, the solar plant is installed in the campus and will be connected to the state govt supply grid. A picture regarding this matter is enclosed further reference.

It should be considered fulfilling the offset of solar energy requirement. A confirmation to this effect will be appreciated.

Attachment(s) included.

Response

Yes the proposed compliance path is acceptable on submission of required documentation and verification during site visit.