(#8281) WWR consideration for base case and design case EPI calculation using Resbuild

Query

As per Appendix 4 of GRIHA v2015 manual, guidelines have been given for the Resbuild tool, which state that WWR has to be 30% for each type of building. Does this value have to be considered for GRIHA basecase EPI and should we consider actual WWR of the project for EPI calculation of Proposed building?

Solution

Yes, the project team can use the actual WWR of the project to perform simulation.