Query
The buildings undergoing GRIHA certification are a part of the thermal power plant campus. As it is not possible to install the Solar PV system at every building terrace, the project team will install the Solar PV at 2-3 places in the campus and the energy generated will be fed in the main grid line of the campus. Is this approach OK? Kindly confirm.
Response
On- ground Solar PV installation is acceptable as long as the designated area for PV installation is within the site boundary (project campus), under the purview of the building owner.