Query
Due to higher percentage of server, IT and data center loads in Data Center buildings, it has much higher EPI compared to GRIHA EPI for 24 hours buildings. Since the Power Usage Effectiveness (PUE) of data centers is around 1.35, is there any exemption given in such cases.
Response
There is no exception provided for Data center buildings. As mentioned in the query process/ equipment loads are simply deducted from the EPI calculations.