Query
As per the Soil Investigation report, the groundwater level for the Project is 0.5M-8.5M. The project site has contours and hence, the Groundwater level has varied range. In this case, do we need to provide a recharge pit?
Solution
Please confirm what is the time frame in which this test was conducted. Project is required to provide a post monsoon water table report. Also recharge of rain water exemption can be as per the local bye laws.
It is suggested to conduct a hydrogeological study of the site to get a better understanding of the groundwater profile at site. The study is generally conducted on large sites and especially for sites where groundwater has fluctuating levels.