Query
The project is installing occupancy sensors in the project. How much savings can be claimed using the same in the energy simulation? What LPD value should be considered in the simulation?
Solution
The LPD in the simulation model must be as per the actual design. However, the project may consider modifying the operating schedule, occupancy schedule and diversity factor which must be consistent with HVAC DBR and electrical DBR.