How can a project comply with the mandatory requirement in Criterion 18 of GRIHA v3, in case of phase wise construction?

Query

How can a project comply with the mandatory requirement in Criterion 18 of GRIHA v3, in case of phase wise construction?

Solution

The client must provide declaration on the letter head that they will install Renewable Energy in future along with tentative sizing and timeline for this installation.

On meeting the documentation requirement, the project will only achieve the mandatory points under criterion 18.