Should the project comply with ECBC mandate in case of an existing transformer?

Query

Should the project comply with ECBC mandate in case of an existing transformer?

Solution

As the transformer is an existing one, the project need not comply with the ECBC mandates for transformers. However, a document signed by the project proponent must be submitted stating that if a transformer is installed in future, then it will comply with ECBC mandates.