The project had no plumbing flow and flush fixtures (Urinal, Water Closet, Faucets etc). Therefore can a part of criterion 8 of SVAGRIHA i.e. building water demand reduction points (3 out of 3) could be awarded to the project.
Answer
If the project has no plumbing flow and flush fixtures (Urinal, Water Closet, Faucets etc), a part of criterion 8 of SVAGRIHA i.e. building water demand reduction points (3 out of 3) will be non-applicable for the project and the project team have to submit the justification for not installing plumbing fixtures in the project along with the alternate provision made for water use (this explanation is required from the client).