(#8626) Methodology for Water Performance Index (WPI) calculation

Query

What is the methodology for WPI calculation in Criterion 16, GRIHA v 2019.

Solution

Water Performance Index (WPI) is the amount of fresh water required per person per day in the project, i.e.

Total fresh water demand of the project annually (domestic/flushing/cooling/irrigation etc. depending on the MEP design) / Total occupancy / No of working days.