In one of our projects a few buildings have been operational for the past one year.
The project is registered under GRIHA v2015 and is yet to apply Provisional rating certification.
However considering few blocks of the project are operational, we're intending to do site audits as per Cr 30 by authorised BEE auditor and submit documentation with respect to final griha rating documentation. Will this be accepted?
Solution
The project will have to apply for the GRIHA provisional rating and submit documentation accordingly. Upon 60-65% occupancy of all the buildings and after the buildings has been operational for more than one year, audit data from a BEE certified auditor will have to be submitted for the final rating.