Query

Does post construction runoff have to be calculated for only the area under development or the entire site? What is the method for calculating the same?

Response

The run off calculation will have to be submitted taking into consideration all the site surfaces (within GRIHA boundary) to demonstrate compliance. The storage capacity of the water bodies, recharging pits, reused water quantity will be used to demonstrate that 90% of the storm water is being managed on site.