A project is in its inception stage with no water supply lines, rainwater storage and sewage treatment plant on site. How can it comply with BIS standards for water quality?

Query

A project is in its inception stage with no water supply lines, rainwater storage and sewage treatment plant on site. How can it comply with BIS standards for water quality?

 

Solution

The project team should take samples of municipal supply water and get those tested. Submit specification sheets of the proposed STP and WTP (for water reuse from captured rainwater) technologies demonstrating that as per their testing, the output water meets the relevant BIS standards.



LABELS:

  • Water and waste water management (Developmental Quality )
  • GRIHALD
  • Have more questions? Submit a request